This webpage provides information about current and proposed development projects in Union Grove. Visit the Village Meetings page for information about upcoming meetings of the Village Board, Plan Commission, and Community Development Authority. Also be sure to follow the Village’s newsletters for more news and announcements.


The Granary (State St. and Mill Ave.)

The Granary development is a 73-unit multi-family development project consisting of five townhouse-style apartment buildings near State St. and Mill Ave. and one commercial building on Main St. The project is the result of a multi-year planning effort to revitalize an old grain mill site near downtown Union Grove. The Granary development has eliminated blighted conditions that existed on these lots and will help support local businesses in the downtown area.

Project Economics
In September 2018, the Village Board approved a development agreement for The Granary, which involved the creation of a tax incremental financing district (TID #5) to help fund the necessary land acquisition, environmental remediation and infrastructure costs associated with the project. The agreement provided that the development will result in $10.0 million of new assessed value and that initial tax increment generated by the development will reimburse the land and infrastructure costs and will provide development incentives of up to $1.3 million (if minimum values are met).

More Information:


The Residences at Dunham Grove (69th Dr. east of Shumann Dr.)

In 2018, Pre/3 purchased the western half of the “Fonk property,” a 45-acre parcel located in the southeast corner of Union Grove on 69th Dr., east of Shuman Dr. The Residences at Dunham Grove will be a residential development consisting of 63 single-family homes and 120 multi-family units (10 buildings with 12 units each). Phase 1 of the project started in fall 2019, and it will be comprised of 23 single-family homes and all of the multi-family units. Phase 2 will be constructed at a future time and will include the remaining 40 single-family homes.

Project Economics
The Village Board approved a development agreement on April 22, 2019. It was subsequently amended on August 26, 2019 to reflect additional sidewalks as recommended by the Plan Commission.  Public hearings and zoning approvals took place at meetings held by the Plan Commission and Village Board in May and June 2019. The development agreement was conditioned upon the creation of a tax incremental financing district (TID #6) to fund the infrastructure needed to serve the development. As part of the agreement, the project will achieve a minimum assessed value of $20.7 million by 2023 and an additional value of $14.2 million by 2029. TID #6 is projected to close by 2040, and an expected $34.8 million will be added to the Village’s property tax base. In addition to adding considerable assessed value and new housing options, the project will result in new water and sewer service to the southeast corner of the Village from Highway 11.

More Information:


Canopy Hill (S. Colony Ave. and 58th Rd.)

Canopy Hill is a 160-acre multi-use housing development that was originally proposed in 2007 but was delayed due to the Great Recession. Canopy Hill has been re-introduced with plans for 240 market rate multifamily units, 202 single family lots and approximately 80 units total of both senior independent and assisted living. The developers are aiming to “provide a wide array of housing to retain existing residents, attract new residents, foster a resurgence of Downtown Main St. and further bolster a top tier school district.”

Project Updates
January 2020 – The Village and developer continue to negotiate terms for a development agreement for Canopy Hill. No timeline is identified at this time for permit applications and construction.

More Information: